Robotics & Physical AIOct 15, 2026
Texas has frozen new data-centre permits after ERCOT's queue grew to 474 GW, a16z writes
a16z wrote on 7 October 2026 that at the end of 2024 Texas's grid operator ERCOT had 63 GW of large new customers in its queue, and that by June the figure had reached 474 GW, more than five times record peak demand and about 90% data centres. Texas then paused. What began as directions for data centres to pay for their own grid upgrades has escalated to a freeze on all new permits. a16z points to developers spamming requests across several sites, many speculative builds with no customer, and local community concerns.
What it means Power hookups, not chips, are becoming the gating step for new AI capacity, and Texas had been one of the easiest places to get one.
Where it came from a16z